Child Care Centre

CHILD CARE CENTRE

Project Timeline

21 Days

Project Budget

$78,000

Area

540m2

Landscape design proposal

  • Supply and install plants as per design
  • Supply and install Playsafe Softfall mulch covering all garden beds.
  • Supply and install fully automatic irrigation system (commercial) covering entire landscape
  • Supply and install artificial turf, Softfall underlay, Geo-textile fabric
  • Supply and install deck x 3, kid kitchen, logs, mud pit and finish it with protection
  • Supply and install sandpit x 3 (Sandstone blocks, foundation, rendering, painting) – Supply and install 30mm drainage cell, geo-textile fabric and infill with kids safe play sand on all three sandpits. – Water-proofing all sides – Supply and install 100mm Agi-pipe to install drainage solution
  • Supply and install Sensory path (deco-path)
  • Supply and install stepping stones
  • Supply and install Decomposed granite porous paving
  • Supply and install wooden planter box on Ground Floor and First floor – Install landscaping liner along insides – Install dripping irrigation system.
  • Supply and install Colorbond fence for bin enclosure in the basement

Conclusion

It was an incredible experience working with a number of different friendly and professional trades people. The Project Manager and Site Supervisor were really supportive and easy to deal with. We managed to finish the project 5 days in advance with a satisfactory result.

The entire team did an amazing job accomplishing the project.